My scope creep project happened pretty recently, and has
not completely been resolved, so I’m interested to stick it out and see what
happens. There is one training course I’m currently working on, and there is no
PM designated. Where I work, we have a designer and a SME on a team. Other
people will only be brought in if necessary. Luckily, for this course I have a
few other designers working with me.
This course is one that has already been created and is
in a revision process so that we can pinpoint what is needed and what exactly
to train students on. The students in the class come from all over the world to
be trained on giving background investigations, as well as perform other
duties. Because the course is already being taught and I have access to the
lesson plans and previous ADDIE paperwork that had been filled out, I can see
what is being taught. I was beginning to re-paper the course (which just means
to update the paperwork and make any necessary changes) and had gotten to the
design phase when the SME made it known she wanted to add three days to the
course.
Here are a few reasons why this is bad: each day costs
money, per student. The amount that a student’s organization will pay for them
to attend class only covers a percentage of the training facility’s cost.
Adding the days to the course would not only cost more, but the papering
process would need to be restarted, meaning we’d lose money from the delays. When
the SME and I finally reached a consensus, she mentioned that the three added
days would not be taking place at our facility. This led to bringing more
people on board to coordinate, spending more money in paying for rental cars
and hotel rooms for students, and having to redo the paperwork once again. (I
also should note that the only reason the team conceded to the SME was because
there was not enough data to back up the idea that these last three days are unnecessary.)
This project began in November, and the course is not
until June. However, the original course date was April, so we’ve already lost
money on having to delay the class. Another designer and I are the leads on
this project, and at this point it’s difficult to see what else could come up to
get us off track; it actually looks like we may make our June date.
If I was a PM, I would have gone back to the analysis
phase once the extra three days were requested and conducted a needs analysis
to see if the extra time is something that is really necessary. Chances are
this analysis would have taken less time to put together than all the paperwork
and coordination for an extended course. I also would have kept the lines of
communication open along the way so that this news didn’t take us by surprise halfway
through the project. Our curriculum manager also has working knowledge of each
course, and had I been in control, I would have brought him in much sooner to
get his take on the changes.